20 people can complete a particular job in 60days if the job has to be conducted in 15 days how many more people are required​

Answers

Answered by harsh15044
0

Step-by-step explanation:

20 people complete the job in 60 days.

So, x people complete the job in 15 days.

Because they are in indirect proprtion,

20*60=15x

=>1200=15x

=>x=1200/15

=>x=80

So, 80 people can do the job in 15 days.