Math, asked by anshraj25, 11 months ago

20 person can do a work in 180
days then how many person will be required to complete that work in 40 days​

Answers

Answered by pauljoshua
2

Answer:

90 persons are needed for working in 40 days

Answered by AbbasaliMansuri
3

Answer:

10 person are do a work 180 days .