Math, asked by Janvi3212, 5 months ago

20 students are assigned the task to clean up a local park in 10 days. After 8 days, 12 students leave the work due to a viral infection. How many more days will the remaining students take to complete the task?

Answers

Answered by tanviarora143
0

Answer:

2 days

Step-by-step explanation:

8 students

answer

Answered by payalchatterje
0

Answer:

Required time is 6 \frac{1}{4}

days.

Step-by-step explanation:

Total number of students are 20.

They take 10 days for complete the task.

So, 20 students take 10 days for complete 1 work.

So, In one day they can do (1/10) work

They worked for 8 days together.

In 8 days the did 8 \times  \frac{1}{10}  =  \frac{4}{5} work.

So, remaining work  = (1 -  \frac{4}{5} ) =  \frac{1}{4}

Now number of students are (20-12)

 = 8

20 students take 10 days

1 students take 200 days

8 students take  \frac{200}{8}  = 25days

So, 8 students do 1 work in 25 days

So,they do (1/4) work in  \frac{25}{4}  = 6 \frac{1}{4}

days.

Similar questions