20 workers can dig a canal in 17 days,working daily 8 hours.How many hours 34 workers need to work daily to complete 8 days​

Answers

Answered by sinhaprisha30
1

Answer:

Let the total number of men to be engaged be x

More length, More labourers (Direct proportion)

Less days, More labourers (Indirect proportion)

Lentgh 26:39Days 6:18Hours per day 9:8⎫⎭⎬::17:x

∴ 26×6×9×x=39×18×8×17⇔x=(39×18×8×17)(26×6×9)⇔x=68

∴ Number of more labourers = (68 -17) = 51

Join The Discussion

Comment*

Related Questions on Chain Rule

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

A. 9

B. 10

C. 11

D. 12

View Answer

If the cost of x metres of wire is d rupees, then what is the cost of y metres of wire at the same rate?

A. Rs. xyd

B. Rs.xd

C. Rs.yd

D. Rs. ydx

View Answer

Running at the same constant rate, 6 identical machines can produce a total of 270 bottles per minute. At this rate, how many bottles could 10 such machines produce in 4 minutes?

A. 648

B. 1800

C. 2700

D. 10800

View Answer

A fort had provision of food for 150 men for 45 days. After 10 days, 25 men left the fort. The number of days for which the remaining food will last, is:

A. 2915

B. 3714

C. 42

D. 54

View Answer

More Related Questions on Chain Rule

Read More: MCQ Type Questions and Answers

Arithmetic Ability

Competitive Reasoning

Competitive English

Data Interpretation

General Knowledge

History

Geography

Current Affairs

Banking Awareness

Computer Fundamentals

Networking

C Program

Java Program

SQL

Database

HTML

CSS

Javascript

PHP

Computer Science

Electrical Engineering

Mechanical Engineering

Civil Engineering

Chemical Engineering

Commerce

Management

Copyright © 2021 Examveda.com Shemale escort

About Us |Terms & Condition |Privacy Policy |Contact Us

Answered by madhucoding1998
4

Answer:

they need to work for 10 hours daily

Step-by-step explanation: