20 workers can finish a piece of work in 30 days. after how many days should 5 workers leave the job so that the work is completed in 35 days.
Answers
Answered by
2
after 15 days should 5 workers leave the job so that the work is completed in 35 days
Answered by
0
after 15 days the worker should leave the job