200 labors need 50 days to construct a road of 4 km long.How many labors are needed to construct 8 km long road in 80 days?

Answers

Answered by saumendrabora
2

Answer:

Step-by-step5 explanation:

50 days 4 km = 200 labours

1 day 1 km = 200x50/4 labours

80 days 8 km = 200x50x8/4x80

= 8000/320

=250 labours