21. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
A) 3 B) 5 C) 7D) Cannot be determined​

Answers

Answered by Anonymous
0

10 women complete the work in 7 days.

10 children complete the same work in 14 days

∴ 1 woman ≡ 2 children

=> 5 women + 10 children = 20 children

By M1D1 = M2D2

= 10×14 = 20×D2

=>D2 = 10×1420 = 7 days.