Math, asked by Keyso, 7 months ago

21 men can dig a trench in 30 days if the work us to be done in 18 days how many more men must employed

Answers

Answered by nigarg82
0

Answer:

14 more men must be employed.

Hope it helps.

Please mark my answer as BRAINLIEST.