Math, asked by ritikroushankumar21, 11 months ago

210 men can complete a piece of work in 44 days, how many days will 280 men take to do it?​

Answers

Answered by gujjarankit
10

Answer:

280 men will complete the whole work in 33 days

Attachments:
Answered by yattipankaj20
10

33 days

Step-by-step explanation:

Number of men = x_1 and x_2

Number of days = y_1 and y_2

x_1\times y_1=x_2 \times y_2\\y_2=\frac{x_1\times y_2}{x_2}\\\Rightarrow\frac{210\times44}{280}\\\Rightarrow\frac{9240}{280}\\\Rightarrow33 days