210 men working 12 hours a day can finish a job in 18 days how many men are required to finish the job in 20 days working 14 hours a day
Answers
Answer:
Step-by-step explanation:210 men can complete a work in 12 hours in 18 days means they worked for (12×18) hours.
so, by inverse variations,
210×12×18
20×14
=162 days
16 men are required to finish the job in 20 days working 14 hours a day
Step-by-step explanation:
No. of men required to complete job in 18 days by working 12 hours a day = 20
No. of men required to complete job in 1 days by working 12 hours a day =
No. of men required to complete job in 1 days by working 1 hour a day =
No. of men required to complete job in 20 days by working 1 hour a day =
No. of men required to complete job in 20 days by working 14 hours a day =
No. of men required to complete job in 20 days by working 14 hours a day =
So, 16 men are required to finish the job in 20 days working 14 hours a day