210 men working 12 hours a day can finish a job in 18 days how many men are required to finish the job in 20 days working 14 hours a day ​

Answers

Answered by prakashwagharalkar4
3

Answer:

Step-by-step explanation:210 men can complete a work in 12 hours in 18 days means they worked for (12×18) hours.

so, by inverse variations,

210×12×18

20×14

=162 days

Answered by wifilethbridge
0

16 men are required to finish the job in 20 days working 14 hours a day ​

Step-by-step explanation:

No. of men required to complete job in 18 days by working 12 hours a day = 20

No. of men required to complete job in 1 days by working 12 hours a day = 20 \times 18

No. of men required to complete job in 1 days by working 1 hour a day = 20 \times 18 \times 12

No. of men required to complete job in 20 days by working 1 hour a day = \frac{20 \times 18 \times 12}{20}

No. of men required to complete job in 20 days by working 14 hours a day = \frac{20 \times 18 \times 12}{20 \times 14}

No. of men required to complete job in 20 days by working 14 hours a day = \frac{20 \times 18 \times 12}{20 \times 14}=15.42

So, 16 men are required to finish the job in 20 days working 14 hours a day