210 men working 12 hours a day can finish a job in 18 days. How many men are required
to finish the job in 20 days working 14 hours a day?
cement​

Answers

Answered by mandeepguraya91
2

Step-by-step explanation:

162 men required to finish the job in 20 days working 14 hours a day. Step-by-step explanation: 210 men working 12 hours can finish a job in 18 days.

Answered by aditisharma126
4

Answer:

210 people = 12 hr. = 18 days

Step-by-step explanation:

162 people = 14 hr. = 20 days