Math, asked by anbuantonyjenit, 3 months ago

210 men working 12 hours a day can finish a job in 18 days.How many men are required to

finish the job in 20 days working 14 hours a day?​

Answers

Answered by mansikamble53
2

Step-by-step explanation:

210 men can complete a work in 12 hours in 18 days means they worked for (12×18) hours.

so, by inverse variations,

= 210x12x18

= 20x14

= 162 days