22. Ram can do 5/8 of a work in 15 days and Mahesh can finish the remaining work in 5 days. In how many days both can do the
work?​

Answers

Answered by andrel75
1

Answer:

20 days

Step-by-step explanation:

ram can do the 5/8 of the work in 15 days and Mahesh 5 days

1-5/8=3/8

so Mahesh 3/8 in 5 days

so 5days+15days= 20days

Answered by adityakumar5155
5

Answer:

60/7 days

Step-by-step explanation:

PLEASE MARK MY ANSWER AS BRAINLIEST

Ram can do 5/8 work in 15 days

=> he can do 1/24 work in single day

Now,

Mahesh can do remaining work(3/8) in 5 days

=>he can do 3/40 work in single day

Now,

Total time = Piece of work  /  (work of ram + work of mahesh) in a single day

Total time = 1 [as there is one work only]  / (1/24+3/40)

                 = 60/7 days