(23. A takes three times as long as B and C
together to do a job. B takes four times as
long as A and C together to do the work. if
all the three can complete the job in 24 days
then the number of days, A alone will take
to finish the job is .. ​

Answers

Answered by shriskandadel
2

Answer:18 days

Step-by-step explanation:a/3= b+c

A+B+C = 24 days

1/a+b+c = 1/24 days

1/a+a/3 = 1/24 days

3/4a= 1/24 days

4a = 72 days

a = 72/4

A takes 18 days to finish the work