23. When is Programme Evaluation and Review Technique (PERT) is used?
a. Advertisement
b. Selling
c. Exchange
d. Evaluating the working programme
Answers
Answered by
0
Answer:
Correct option is d. Evaluating the working programme.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
Answered by
0
Answer:
d.Evaluating the working programme