23. When is Programme Evaluation and Review Technique (PERT) is used?

a. Advertisement

b. Selling

c. Exchange

d. Evaluating the working programme

Answers

Answered by harman6670
0

Answer:

Correct option is d. Evaluating the working programme.

Explanation:

Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.

Answered by mirinshayousuf
0

Answer:

d.Evaluating the working programme