24. A can do a job in 20 days. He works for 5 days and finishes
1/4 of the total work. Then B comes and finishes the
remaining work in 15 days. How many days A and B together
will take to finish the job?
(a) 17.5 days
(b) 15 days
(c) 10 days
(d) None of these
Answers
Answered by
0
Answer:
(a) 17.5 days
is your answer dear