24. In a company, the hourly rate wages guaranteed is 0.50 paise per hour. The standard time forproducing one dozen article is 3 hours. The actual time taken by the worker to produce 20 dozenarticles is 48 hours. The earnings of a worker under rowan plan is:
A. Rs. 27
B. Rs. 28
C. Rs. 28.80
D.Rs. 30
Answers
Answered by
0
Explanation:
d ..............or b....
thanks
Answered by
0
Answer:28.80
Rowan premium bonus plan:
(actual time take.rate per hour)+(time taken/standard.acutal time taken.rate per hour hour)
T.E=(48×0.50)+(12/60×48×0.50)
=28.80