Math, asked by maroof1, 1 year ago

24 labours can complete a building in 8 months. how many will be required to contract another building of triple size as previous building in 10 months?

Answers

Answered by adi1233
0
if 24 labors are completing a building in 8 months then, 30 labors will be needed .
Answered by PravinRatta
0

Answer:

58 people required to complete the project.

Step-by-step explanation:

Apply work and time formula,

M1 D1 H1 / W1 = M2 D2 H2 / W2

where, M= no. of person

H = Time required to complete the work.

D = day required to complete the work.

W=  Work

24 * 8/ 1 = x * 10/3      (  building of triple size as previous building , so w1 = 1                    and w2 = 3)

24 * 8 = 10 * x /3

24 * 8 * 3 /10 = x

x = 576/10

x = 57.6 = 58

58 people required to complete the project.