Math, asked by shrishti806, 10 months ago

24 Man can do a work in 35 days.How many men are required to complete the work in 21 days.

A)38
B)40
C)36
D)42

Plzzz answer with step by step explanation ​

Answers

Answered by himanshiranjan1404
4

Answer:

hope this image will help you and thank me and mark me as brainlist.

Attachments:
Answered by KrishivMuthu
16

Step-by-step explanation:

If 24 men can do it in 35 days..

Time taken by a man is = 24×35 = 840 days

No of men required to complete in 21 days

= 840÷21 = 40

Therefore 40 men are required to complete the work in 21 days ...

THANK YOU.. PLS MARK ME AS THE BRAINLIEST...