24 men can complete a work in 12 days after 6 days of work 6 men left the job in how many days will take to complete the remaining work
Answers
Answered by
1
Concept of man days is required to solve this problem.
24 * 12 = Man days
24 men worked for 6 days and they will complete 24 * 6 Man days
Remaining men = 24-6 = 18
Remaining Man days = 24*12 - 24*6 = 144 Man days
18 men will complete it in 144/18 = 8 days