24 men can complete laying a stretch of road in 10 days.How many men can finish the same work in 8 days?

Answers

Answered by Peacekeeper
2
No. Of men*days=Amount of work
24*10=240
Let us take no of men as X.
Therefore,
x*8=240
x=240/8
x=30 men is the answer.