24 men can do a piece of work in 16 days they start the work but after 8 days 12 men leave the work find the number of days in which total work become complete
Answers
Answered by
0
Answer:
Hlo everyone
Step-by-step explanation:
16 days yo bro
Answered by
0
The total number of days is 16
Given data :
24 men completes the work in 16 days.
After 8 days of work,12 men left.
Let,the total work = x
So,
24 men in 16 days complete = x
24 men in 1 day complete = x/16
24 men in 8 days complete = 8x/16 = x/2
Rest amount of work = (x-x/2) = x/2
Men left = (24-12) = 12
Now,
24 men complete x/2 work = 8 days
1 man completes x/2 work = 8×24 days
12 men complete x/2 work = (8×24)/12 = 16 days (answer)