Math, asked by jaswanth05854, 5 months ago

24 men do a work in 35 days.
HOW many men are required
to complete the work in 21 days

a)38 b)40 c)36 d)48​

Answers

Answered by syedakanza
3

Answer:

40

Step-by-step explanation:

this is inverse proportion

As the days are decreased, number of men increase and vise versa

24 * 35 = X * 21

840. =X * 21

840/21. = X

40. = X

Similar questions