Math, asked by guptakhushi2352, 1 year ago

24 men working 8 h a day can finish a work in 10 days. working at a rate of 10 h a day, the number of men required to finish the work in 6 days is

Answers

Answered by aanal
2
24 men, 8 hr, 10 days
? 10 hr, 6 days
=10×6/24×8×10
=1/32 men
Answered by mysticd
5

Answer:

\red { Number \: men \: required \: to}

\red { finish \: the \: work }

\green { = 32 }

Step-by-step explanation:

 Here, we \:have \: three \: quantities \: i.e \\number \: of \: men ,\: number \: of \: hours\\per \: day \: and \: number \: of \: days

 number \: of \: men (x_{1} ) = 24,

 number \: of \: hours \: per \:day (h_{1}) = 8

 Number \: of \: days (d_{1}) = 10

 number \: of \: men (x_{2} ) = \red{?}

 number \: of \: hours \: per \:day (h_{2}) = 10

 Number \: of \: days (d_{2}) = 6

 m_{2}\times h_{2}\times d_{2} =m_{1}\times h_{1}\times d_{1}

 \implies m_{2}\times 10\times 6 =24 \times 8\times 10

\implies m_{2} = \frac{24\times 8 \times 10}{10\times 6 }\\= 32

Therefore.,

\red { Number \: men \: required \: to}

\red { finish \: the \: work }

\green { = 32 }

•••♪