Math, asked by sonuagrl5529, 8 months ago

24 men working 8 hours a day can finish a work in 10 days. Working at the rate ogf 10 hours a day, the number of men required to finish the same work in 6 days is?

Answers

Answered by riyas30
3

Answer:

Original measured work was for: 24 men, 8 hours per day, x 10 days = Total work content of 1,920 hours

Revised work schedule is: 1,920 hours divided by 6 days = 320 hours per day divided by working 10 hours per day = 32 men As we already have 24 men,

The Answer: Is that we will require another 8 men to the existing workforce of 24 men = 32 men in total.

Similar questions