24 men working 8 hours a day can finish a work in 10 days. Find the number of men required to finish the same work in 6 days working 5 hours a day? (a) 60 (b) 64 (c) 80 (d) 72 (e) none of these

Answers

Answered by shubhamkumarsaha
1
Sorry for too much solving disturbances.
Well, the answer will be B 64 men
Hope it helps
Please mark me the brainliest.