Math, asked by cheruvupalligovinda, 1 year ago

24 men working at 8 hours per day can do a piece of work in 15 days how many days can 20 men working at 9 hours per day the same work

Answers

Answered by TooFree
140

Answer:

16 days


Step-by-step explanation:

24 men working at 8 hours per day can do the work in 15 days

Amount of work = 24 x 8 x 15 = 2880 man-hour


Find the number of days needed for 20 men working 9 hours a day:

Time number of man-hour = 20 x 9 = 180

Number of days needed = 2880 ÷ 180 = 16 days


Answer: 16 days

Answered by knjroopa
64

Answer:

16 days

Step-by-step explanation:

Given 24 men working at 8 hours per day can do a piece of work in 15 days how many days can 20 men working at 9 hours per day do the same work.

24 men work 8 hours per day does the work in 15 days

20 men work 9 hours per day in how many days?

  24 x 8 x 15 = 2880 and 2880 / 20 x 9 = 2880 /180 = 16 days

Alternatively we can do as

 15 x 24/20 x 8/9  = 16 days