24 men working at 8hrs per day can do a work in 15 days. in how many days can 20 men working at 9hrs pet day do the same work

Answers

Answered by Anonymous
4

hey frnd☺☺☺
----------------------
The job takes 24 men x 8 hrs/day x 15 days = 2880 man-hours
------------
2880 man-hours/(20 men x 9 hours/day) = 16 days
-----------------------
Another method:
15 days * 24/20 * 8/9 = 16 days .