24 persons can big apond in 12 days.then how many persons can dig the pond in 8 days?
Answers
Answered by
3
in 12 days number of person required to dig a pond =24.
so,number of person required to dig the pond in 1 day =24×12.
and number of person required to dig the pond in 8 days =(24×12)/8 =36
so,36 persons required to dig a pond in 8 days..
hope it will help....
so,number of person required to dig the pond in 1 day =24×12.
and number of person required to dig the pond in 8 days =(24×12)/8 =36
so,36 persons required to dig a pond in 8 days..
hope it will help....
rana9679822:
thank u
Answered by
1
24 persons can big apond in 12 days.then 36 persons can dig the pond in 8 days