24 workers can build a wall in 15 days. How many days 9 workers take to build a similar wall?
Answers
Answered by
8
Let the 9 workers take to build a similar wall in x days
Applying Proportion method
24 15
9 x
x=135/24 days
Answered by
10
Hope it's helpful to you
Please mark as brainleist
Please mark as brainleist