24 workers can building a well in 15 days how many days are well 9 workers take to building a simple Bird
Answers
Answered by
2
Answer:
Mark tis as branliest
Step-by-step explanation:
1 worker will build the wall in 24×15=360 days
Days taken by 9 workers =360÷9=40 days
Answered by
0
Answer:
24 workers need =15days
:•1 workers need=15/24days
=5/8days
:•9workers need =5/8* 9.
=45/8=5days and 20min approx