24 workers can do a piece of work in 10 days how many workers should be added to complete the work in 8 days​

Answers

Answered by thomaslol
5

Answer:

6 workers should be added

Step-by-step explanation:

240 workers can do a piece of work in 1 day.

240/8 = 30

30 - 24 = 6