24 workers working 6 hours a day can finish a piece of work in 14 days. If each worker works 7 hours a day, find the number of workers to finish the same piece of work in 8 days.
Answers
Answered by
2
Answer:
4 hours x 12 days=48 total hours worked
48 hours x 10 men=480 man/hours
1 man/480 total hours=1/480th of the work done per man per hour
8 x 6 x 1/480=1/10 work done per day
1 work / 1/10 work done per day=10 days necessary to finish the work
Step-by-step explanation:
Answered by
1
NO. OF WORKERS . NO. OF HOURS/DAY NO. OF DAYS
24 6 14
X 7 8