24 workers working 6 hours a day can finish a piece of work in 14 days if each worker works 7 hours a day find the number of workers to finish the same piece of work in 8 days
Answers
Answered by
7
if 24 workers works 6hrs so (24×6=144 Hrs per day ),then 14 days (144×14=2016hrs required to finish work with 24 workers)
so ur asked to finish work in 8days with 7 hrs per day we need to work per day 252 hrs so 36 workers required to finish work with 8days 36×7=252, 252×8=2016hrs
so ur asked to finish work in 8days with 7 hrs per day we need to work per day 252 hrs so 36 workers required to finish work with 8days 36×7=252, 252×8=2016hrs
Answered by
11
Answer:
36
Step-by-step explanation:
We are given that 24 workers working 6 hours a day can finish a piece of work in 14 days
Let be the work done by 24 workers , be the no. of workers , be the no. of days they worked and no. of hours per day they worked
Now we are supposed to find the number of workers to finish the same piece of work in 8 days if each worker works 7 hours a day
Let x be the no. of workers
Let be the work done by x workers , be the no. of workers , be the no. of days they worked and no. of hours per day they worked
Formula :
Substitute the values
Hence the number of workers to finish the same piece of work in 8 days is 36
Similar questions