24 workers working 8 hours a day can finish a piece of work in 10 days find the number of worker required to finish the work in 6 days 10 hours a day
Answers
Answered by
16
Answer:
32 workers are required to finish the work in 6 days 10 hours a day
Step-by-step explanation:
Given that 24 workers working 8 hours a day can complete work in 10 days
24 workers working for 8 hours means
Then, 24 workers work for 10 days means
Thus, total work
Now, let workers are required to finish the work in 6 days 10 hours a day
Thus,
Hence, 32 workers are required to finish the work in 6 days 10 hours a day