Math, asked by banshul876, 6 months ago

24 workers working 8 hours a day can finish a piece of work in 10 days. Find the number
of workers required to finish the work in 6 days working 10 hours a day.

Answers

Answered by amankrshaw15
0

Answer:

24 men working 8 hrs / day can do a piece in 15 days

∴ Total work units =24×8×15

=2880

No.of days required by 20 men, working at

a hrs/day=

20×9

2880

16 days