24 workers working 8 hours a day can finish a piece of work in 10 days. Find the number
of workers required to finish the work in 6 days working 10 hours a day.
Answers
Answered by
0
Answer:
24 men working 8 hrs / day can do a piece in 15 days
∴ Total work units =24×8×15
=2880
No.of days required by 20 men, working at
a hrs/day=
20×9
2880
16 days