24men can do a work in 35 days.how many men are required to complete the work in 21 days

Answers

Answered by 236019tcs95
2

If 24 men can do it in 35 days...

Time taken by a men= 24×35=840 days

No of the men required to complete in 21 days

= 840÷21 = 40

Therefore 40 men are required to complete the work in 21 days