Math, asked by bhavyagarwal11sep20, 7 months ago

25: 40 men can dig a trench in 30 days. How many more men should be employed if the job is
to be finished in 10 days?​

Answers

Answered by mishikhan
0

Answer:

Friends…!

If 8 men can dig a trench in 15 days, .

Total man-days required to dig the trench

= 8 men × 15 days

= 120 man-days

how many more men should be engaged to finish the work in 6 days?

Now the work has to be completed in 6 days

No of men required to finish the job in 6 days

= 120 men-days / 6 days

= 20 men

Total 20nen will be required to complete the job in 6 days. As 8 men are already on job hence additional men required will be

Step-by-step explanation:

Answered by mairahasan28
1
more 20 men will be employed to complete the work