25. A and B individually can do a work in 8 hours
and 12 hours respectively. A worked first for 2
hours and then left. How long will B take to
finish the remaining part of the work ?
Answers
Answered by
1
Answer:
B will take 9 hours to complete the remaining work.
Step-by-step explanation:
Let the work to be done be denoted by W
Time taken by A to complete the work = 8 hours
Rate at which A does the work =
Time taken by B to complete the work = 12 hours
Rate at which B does the work =
Work done by A in the 2 hours = =
Work to be completed by B after A leaves = =
Rate of work done =
∴ Time taken =
=
= 3 × 3
= 9 hours
Hence B will take 9 hours to complete the remaining work.