25. A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together
can finish the work in 12 days, find the time taken by B to finish the work.
CSE EXAMINATION QUESTIONS FOR PRACTICE
Answers
Answered by
1
Answer:
step by step explanation:
let the time taken by B is 'x'
nd the time taken by A is 'x-10'
1/x+1/x-10 =1/12
solve this equation carefully nd u will get your answer
Similar questions