25 labourers are employed to complete a task in 8 days.How many more labourers are required to complete the task in 5 days
Answers
Answered by
12
25 labourers are employed to complete a task in 8 days. How many more labourers are required to complete the task in 5 days?
- 25 labour complete work in 8 days!
Let the number of labour be which completes work in 5 days.
So, 40 labours are required to complete work in 5 days.
Answered by
1
Step-by-step explanation:
25 labour complete work in 8 days!
Let the number of labour be \bold{x}x which completes work in 5 days.
\bold{\mathtt{5x\:=\:8×25}}5x=8×25
\bold{\mathtt{x\:=\:8×25÷5}}x=8×25÷5
\bold{\mathtt{x\:=\:40}}x=40
So, 40 labours are required to complete work in 5 days.