25 labourers can build a wall in 4 days. IF only 20 labourers report for work, the wall be built in
5 days
3 days
6 days
none of these
sharmashree2008:
ok
Answers
Answered by
2
Given :-
25 labours can build a will in = 4 days.
Labours report for work = 20 .
To Find :-
How many days will be needed to build the same wall ?
Solution :-
M1 = 25 labours .
M2 = 20 labours.
D1 = 4 days.
D2 = Let x days.
we know that, when work is same ,
M1 * D1 = M2 * D2 .
so,
→ 25 * 4 = 20 * x
→ 100 = 20x
→ x = 5 days. (Ans.)
Hence, 20 labours can build the same wall in 5 days.