25 labourers
ourers are employed to complete a task in 8 days. How many more laboure
ed to complete the task in 5 days?
required to comp
Answers
Answered by
3
Answer:
25 labour completes work in 8 days
let no. of labour be x which completes work in 5 days
5x=8*25
x=8*25/5
x=8*5
x=40
so 40 labour is required to complete work in 5 days
Answered by
1
Answer:
25 labour in 8days
5days=? x
25x=8*5