Math, asked by Mdamaan2117, 1 year ago

25 man can do a work in 36 days in how many days will 15 men do it

Answers

Answered by shreekant16
0

Answer:

60 days

Step-by-step explanation:

25 men done a work in 36 days

then

1 man done the work in 36×25 days

so,

15 men done the work in 36×25/15 days = 60 days

Answered by jaswasri2006
32

let the no.of. days be x

so ,

36 * 25 = x * 15

⇒ x = (36*25)/15 = 12 * 5 = 60 days

Thus ,

The Required days is 60 days