25 man can do a work in 36 days in how many days will 15 men do it
Answers
Answered by
0
Answer:
60 days
Step-by-step explanation:
25 men done a work in 36 days
then
1 man done the work in 36×25 days
so,
15 men done the work in 36×25/15 days = 60 days
Answered by
32
let the no.of. days be x
so ,
36 * 25 = x * 15
⇒ x = (36*25)/15 = 12 * 5 = 60 days
Thus ,
The Required days is 60 days