25 men are employed to do a piece of work ,which they could finish in 20 days,but 5 men drop out at the end of every 10 days ,the time in which the work will be completed is?

Answers

Answered by Anonymous
12

Actual work done

=(25×15)+(25+10)×8

=655 men

Time required by 25 men to complete this work is -

= 655/25

=26.2Days

Attachments:
Answered by Anonymous
9

Answer is 26.2 Days.

Hope it helps.