25 men can complete a work in 42 days. how many more men are required,if the work is to be completed in 35 days​

Answers

Answered by gurmeetkaur6780
6

Answer:

33 men are required to complete work in 35days

Answered by aburaihana123
0

Answer:

30 men were required to complete the work in 35 days.

Step-by-step explanation:

Given: 25 men can complete work in 42 days.

To find: Total number of men required to complete the work in 35 days

Formula used: M_{1} D_{1}  = M_{2} D_{2}

Solution:

Given that

25 men can complete a work in 42 days.

The number of men doing a work and the number of days taken is in inverse proportion.

We have to find how many men are required to complete the work in 35 days.

Let us take

Number of men M_{1}  = 25

Number of days D_{1}  = 42 days

M_{2}   = ?

D_{2}  = 35 days

According to the given condition,

M_{1} D_{1}  = M_{2} D_{2}

25 × 42 = M_{2} × 35

1050 = M_{2} × 35

M_{2} = \frac{1050}{35}

M_{2} = 30

30 men are required to complete 35 days.

Final answer:

30 men were required to complete the work in 35 days.