25 men can do a piece of work in 32 days. How many days would 8 men take to do the same work
Answers
Answered by
2
Step-by-step explanation:
Days taken by 25 mens to do the work= 32
Days taken by 8 mens to do the work= x
32:x= inverse of 25:8
32:x::8:25
====> Product of extremes= 32×25
====> Product of means= 8x
8x=32×25
x=32×25/8
x=25×4
x=100 days or 3 months 10 days.