25 men were employed to do a piece of work in some days. After 15 days, 10 more men were engaged and the work was finished in 23 days. In what time would they finish the work if extra men were not employed?
plz do it...
Answers
Answered by
2
Answer:
total number of days that they would have needed to finish the work is 15 + 11.2= 26.2 days.
Step-by-step explanation:
brainlist
Answered by
2
Answer:
26.2days
Step-by-step explanation
If each person does X work and in the last 8 days (as the total work was finished in 23 days as mentioned. So 23-15 is 8 days).
35 men worked then total work done in the last 8 days is 35 * 8 *X = 280X.
Now if the original number of men was maintained then 280X/25X = 11.2 days.
Thus, total number of days that they would have needed to finish the work is 15 + 11.2= 26.2 days.