25 men working 8 hours a day do a job in 63 days .how long would 45 men take to finish the job working 7 hours a day​

Answers

Answered by rahul123487
2

25 men working 8 hours in a day

a job in 63 days

how long would 45 men take to finish the job working 7 hours in day

Answered by ItzBrainlyPrince
17

AnSwEr :-

  • 25 men working 8 hours a day do a job in 63 days .how long would 45 men take to finish the job working 7 hours a day

GivEn :-

  • 25 Men Working 8 hours a day can do a job in 63 days.

To FinD :-

  • The Number if days taken by 45 Men to finish the work in 7 hours a day.

SoluTioN :-

We are required to find the no of days taken by 45 Men to complete same piece of work but in 7hour's a day.

Total Work Remain same on both sides.

Let us say That Number of work taken by 45 Men be 'x'

According to the question

 \boxed{ \bold{ \red{men \times hrs \times day = same \: on \: both \: sides}{} }{} }{}

25 \times 8 \times 63 = 45 \times 7 \times x \\  \\  \frac{25 \times 8 \times 63}{45 \times 7}   \\  \\  \bold{ \red{hence \: x = 5 \times 8 = 40 \: days}{} }{}

'Hence it takes 40 days to complete the work done by 45 Men for 7 hours per day..'