25 men working 8 hours in a day
a job in 63 days
how long would 45 men take to finish the job working 7 hours in day
Answered by
17
AnSwEr :-
- 25 men working 8 hours a day do a job in 63 days .how long would 45 men take to finish the job working 7 hours a day
GivEn :-
- 25 Men Working 8 hours a day can do a job in 63 days.
To FinD :-
- The Number if days taken by 45 Men to finish the work in 7 hours a day.
SoluTioN :-
We are required to find the no of days taken by 45 Men to complete same piece of work but in 7hour's a day.
Total Work Remain same on both sides.
Let us say That Number of work taken by 45 Men be 'x'
According to the question
'Hence it takes 40 days to complete the work done by 45 Men for 7 hours per day..'
Similar questions
Math,
4 months ago
Math,
4 months ago
English,
4 months ago
Environmental Sciences,
8 months ago
Hindi,
8 months ago
Environmental Sciences,
1 year ago