Math, asked by Srishti4111, 1 year ago

25 men working 8 hours a day do a job in 63 days.how long will 45 men take to finish the job working 7 hours a day.

Answers

Answered by ukbroters
30
you will get answer ..
Attachments:

krishnasri99: tq very much bro
ukbroters: well come
ayu643: plz can u arite again i dont undrstand how it wil come
Answered by luckytulsi91
10

Answer:

25 men can do a work (P) in 6 days working 8 hours a day. So we have the equation for the amount of production:

25 men * 6 days * 8hrs/day = P.

Solving the first equation for P:

P = 1200 man-hours

How many hours a day must 30 men have to work in order to finish a work twice as great in 8 days? This gives us another equation:

x * 30 men * 8 days = 2P

Solving the second equation for P:

P = .5 * x * 30 men * 8 days

P = 120x man-days

Now using the two equations to solve for x:

120x man-days = 1200 man-hours

120x man-days / 120 man-days = 1200 man-hours / 120 man-days

x = 10 hrs/day